Wednesday, December 17, 2014

Zamsureco-1 announces 3-hour brownouts daily


PAGADIAN CITY: It’s here again.

The National Grid Corporation of the Philippines (NGCP) is implementing power curtailment in Zamboanga del Sur as the Pulangi IV hydroelectric power plant in Bukidnon is functioning way below its capacity.

Zamboanga del Sur Electric Cooperative-1 (Zamsureco-1) says the notice took effectivity last Monday, Dec. 5.

Liberal Cabatcha, Zamsureco-1 information officer, said NGCP informed them that the 255-megawatt Pulangi IV hydroelectric plant, also known as Pulangi Dam, could only generate 20-MW.

Pulangi IV uses two reservoirs, produced by damming the Pulangi River, to supply water to a run-of-the-river hydroelectric power plant.

Cabatcha explained that Zamsureco-1 member-consumers will experience three-hour brownouts daily.

The power cooperative is receiving 22 MW power supply daily but their power demand is 30-MW.

He said that there is no information yet as to when the power situation will be normalized.

Aside from this, Zamsureco-1 gives out advisories now and then due to their placing of power lines inside Camella Homes at Tiguma, this city.

Though areas affected may be selective; still the power cooperative tells its consumers to “take all necessary measures to protect their appliances and electrical equipment.”